Case Studies
Grandstand Project
Situation: Narrows High School in Narrows, Virginia, needed a new 1250 seat grandstand
for their sports facility. The grandstands were to be constructed on a
steep hillside with a 2:1 slope with approximately 20’-0 of soft
fill soils. The steep slope of the hill made it difficult to use and maneuver
heavy equipment required with other deep foundation systems. There was
also a tight timeline for the construction of the grandstand as it had
to be installed within a 30-day time frame in order to be ready by the
beginning of school and their football season. Ram Jack was added to the
design team to provide a solution that would handle the design loads,
be fast, efficient and long-lasting.
Solution: The design loads consisted of vertical loads of up to 57 kips and lateral
loads comprising of sway and wind of up to 30 and 8 kips per support line,
respectfully. Helical piles were designed to support the vertical loads.
Helical anchors were designed to resist the lateral loads. Due to the
elevation of the girders for the grandstand and the steepness of the hill,
concrete pile caps were not an attractive alterative because of the form
work and the amount of concrete required to be pumped up the hill. Therefore,
a steel pile cap was designed that could be attached directly to the helical
piles and anchors.
Conclusion: Electing to use Ram Jack’s deep driven steel foundation system saved
the school district considerable time, labor, mess and expense. The helical
piles, anchors and support caps were installed in 5 days. The grandstand
structure was erected the following 5 days. Ram Jack helical piles and
anchors redefine the term “INSTANT FOUNDATION.”